As per reports, lane closures are scheduled at the Interstate 78 Toll Bridge’s Express E-ZPass facility in Williams Township from Thursday (20 March).
• The closures are for installing new concrete-slab pavements at the 15-year-old facility. Scheduled closures include:
• From 1900 hours local time on Thursday (20 March) to 0500 hours local time on Friday (21 March), both westbound lanes will be closed for saw-cutting.
• From 0500 hours local time to 2100 hours local time on Friday (21 March), one lane will reopen temporarily.
• From 2100 hours local time on Friday (21 March) to 0500 hours local time on Tuesday (24 March), both lanes will be closed for concrete pouring and curing.
• Additional closures may occur from 27 March to 31 March, subject to weather and other factors.