Road closure scheduled in Guadalajara from Tuesday (10 March)

LowSpain2026-03-10T00:00:00Z

As per reports, the Guadalajara City Council announced milling and asphalting works on Dos de Mayo Street in Guadalajara, resulting in traffic closures during the maintenance period from Tuesday (10 March) to 26 March.

• Authorities indicated that the works require the temporary closure of Dos de Mayo Street during the execution of the maintenance operations.
• The project is divided into three phases covering different sections of the road corridor.
• Phase one, scheduled from Tuesday (10 March) to 17 March, covers the section between Avenida Pedro Sanz Vázquez and Calle del Río.
• Phase two, scheduled from Friday (13 March) to 18 March, covers the section between Calle del Río and Fernández Galiano.
• Phase three, scheduled from 16 March to 26 March, covers the section between Fernández Galiano and Avenida del Ejército.
• Authorities indicated that due to overlapping work phases, Dos de Mayo Street remains fully closed on 16 March and 17 March.
• Officials confirmed that the taxi stand has been temporarily relocated to Avenida del Ejército, with coordination measures in place to maintain access to nearby facilities including the municipal cemetery.